1. For the furnace body of the new equipment, before commissioning, carefully check whether the gas meets the requirements of the low-nitrogen burner; check whether the detection instruments on the gas supply pipeline are normal and whether the pipeline valves are opened and closed normally, and whether it is convenient for future use and maintenance.
2. For the pipelines of new equipment, the reliability of equipment and the tightness of pipelines should be carefully checked for all pipelines.
3. Users who use their own gasification stations must ensure that the gas supply volume and gas supply parameters meet the requirements for safe combustion.
4. Operators carefully read the equipment operation instructions and master the knowledge and methods of safe operation.
5. Before turning on the low-nitrogen burner, check whether the gas valve is open, otherwise the burner will not work.
6. It is recommended to press the power control button on the control cabinet. At this time, the digital display will flash the temperature in the furnace at that time. The temperature of the newly installed furnace body is the ambient temperature.
7. It is recommended to press the fan control button, and the fan on the furnace body will work. If the fan is damaged at this time, the control cabinet will be automatically protected from entering the next step.
9. When the low-nitrogen burner receives signals that are not conducive to combustion (eg: combustion failure, unstable air pressure, circuit problems), etc., the combustion controller will immediately shut down the gas and send out an alarm signal.
10. If the low-nitrogen burner alarms, it must be manually reset by the operator after the fault is resolved before it can continue to work.
11. For the operation of the entire equipment, the operator should refer to the furnace safety operation regulations and production process requirements for operation.
12. When adjusting the control temperature according to the requirements of the production process, the operator should refer to the manual of the intelligent numerical control table for scheduling.
1. For the furnace body of the new equipment, before commissioning, carefully check whether the gas meets the requirements of the low-nitrogen burner; check whether the detection instruments on the gas supply pipeline are normal and whether the pipeline valves are opened and closed normally, and whether it is convenient for future use and maintenance.
2. For the pipelines of new equipment, the reliability of equipment and the tightness of pipelines should be carefully checked for all pipelines.
3. Users who use their own gasification stations must ensure that the gas supply volume and gas supply parameters meet the requirements for safe combustion.
4. Operators carefully read the equipment operation instructions and master the knowledge and methods of safe operation.
5. Before turning on the low-nitrogen burner, check whether the gas valve is open, otherwise the burner will not work.
6. It is recommended to press the power control button on the control cabinet. At this time, the digital display will flash the temperature in the furnace at that time. The temperature of the newly installed furnace body is the ambient temperature.
7. It is recommended to press the fan control button, and the fan on the furnace body will work. If the fan is damaged at this time, the control cabinet will be automatically protected from entering the next step.
9. When the low-nitrogen burner receives signals that are not conducive to combustion (eg: combustion failure, unstable air pressure, circuit problems), etc., the combustion controller will immediately shut down the gas and send out an alarm signal.
10. If the low-nitrogen burner alarms, it must be manually reset by the operator after the fault is resolved before it can continue to work.
11. For the operation of the entire equipment, the operator should refer to the furnace safety operation regulations and production process requirements for operation.
12. When adjusting the control temperature according to the requirements of the production process, the operator should refer to the manual of the intelligent numerical control table for scheduling.