Precautions for gas engine commissioning and maintenance


Gas engine commissioning and maintenance are very important. The following editor will introduce you to the precautions for gas engine commissioning and maintenance.


1. When the gas burner fails to ignite the second time continuously, the burner should be stopped to check whether the gas supply system of the burner is normal and whether the circuit connection is correct. The burner can be restarted only after the fault is eliminated.


2. It is strictly forbidden to knock or rub the gas supply pipeline with a wrench or metal rod to avoid static electricity or sparks.


3. It is strictly forbidden to smoke, weld, cut and other illegal operations at the gas supply valve group or pipeline flange surface.


4. It is strictly forbidden to perform any open flame test near the pipeline, valve group and pressure regulating valve to avoid major accidents.


5. Test whether there is fuel in the gas supply pipeline, usually with a gas low pressure gauge.


6. In the gas supply pipeline, even if it has been emptied, there is residual gas or droplets on the pipe wall. If there is static sparks and open flames, it will also cause combustion.


7. When the gas supply pipeline is ventilated and the valve group has a fault and needs to be disassembled, the main valve at the front end of the valve group must be cut off first, and then the gas in the pipeline from the main valve to the valve group must be vented before the valve group can be disassembled and repaired.


8. During the commissioning work, the gas must be used carefully and safely.


9. It is forbidden to use non-explosion-proof electrical tools on site.


10. Before starting the burner, the gas supply pressure test must be performed to check for leaks. After confirming that it is normal, simulated operation can be performed.


11. Explain the safety operation precautions to the burner purchaser in detail.


12. When the burner is not in use, inform the burner purchaser to cut off the main gas supply valve and the main power switch.


13. It is recommended not to debug the burner at night.


14. At the end of the commissioning, the operator should be organized to train the use and operation direction, and establish an operation process if necessary.


  • Requirements for gas pipeline connection of household gas burning appliances
  • Safety control requirements for natural gas boiler burners
  • Introduction to boiler combustion equipment
  • Basic introduction to crude oil burners
  • Test methods for oil leakage, oil dripping and air tightness of integrated oil b
  • Several special methods for repairing burner faults
  • Reasons for high gas consumption of gas boilers
  • Introduction to the price of oil-fired boilers and the role of oil tanks
  • Explanation of the natural gas consumption and protection device of a 4-ton gas
  • How to use and maintain the burner of a gas boiler

Back

Precautions for gas engine commissioning and maintenance


Gas engine commissioning and maintenance are very important. The following editor will introduce you to the precautions for gas engine commissioning and maintenance.


1. When the gas burner fails to ignite the second time continuously, the burner should be stopped to check whether the gas supply system of the burner is normal and whether the circuit connection is correct. The burner can be restarted only after the fault is eliminated.


2. It is strictly forbidden to knock or rub the gas supply pipeline with a wrench or metal rod to avoid static electricity or sparks.


3. It is strictly forbidden to smoke, weld, cut and other illegal operations at the gas supply valve group or pipeline flange surface.


4. It is strictly forbidden to perform any open flame test near the pipeline, valve group and pressure regulating valve to avoid major accidents.


5. Test whether there is fuel in the gas supply pipeline, usually with a gas low pressure gauge.


6. In the gas supply pipeline, even if it has been emptied, there is residual gas or droplets on the pipe wall. If there is static sparks and open flames, it will also cause combustion.


7. When the gas supply pipeline is ventilated and the valve group has a fault and needs to be disassembled, the main valve at the front end of the valve group must be cut off first, and then the gas in the pipeline from the main valve to the valve group must be vented before the valve group can be disassembled and repaired.


8. During the commissioning work, the gas must be used carefully and safely.


9. It is forbidden to use non-explosion-proof electrical tools on site.


10. Before starting the burner, the gas supply pressure test must be performed to check for leaks. After confirming that it is normal, simulated operation can be performed.


11. Explain the safety operation precautions to the burner purchaser in detail.


12. When the burner is not in use, inform the burner purchaser to cut off the main gas supply valve and the main power switch.


13. It is recommended not to debug the burner at night.


14. At the end of the commissioning, the operator should be organized to train the use and operation direction, and establish an operation process if necessary.


RIELLO

Shanghai Qigu Technology Co., LTD
Block I-J, 14th Floor, Greenland Kechuang Building, 201 Ningxia Road, Putuo District, Shanghai
CHINA China,200333
Burner:Contact +08613761094501
Boiler:Contact +08613761094501
Fax :+08613761094501
E-mail:pittsenli@gmail.com


© Qigu Technology – copyright


Navigation

About Us
Burner
Low nitrogen burner
High temperature burner
Special burner
After service
Company
Contact

Networks

International
België/Belgique (Belgium)
Canada
中国 (China)
Hrvatska (Croatia)
Česká Republika (Czech Republic)
France (France)
Deutschland (Germany)
Magyarország (Hungary)
Italia (Italy)
Latvija (Latvia)
Polska (Poland)
România (Romania)
Россия (Russia)
España (Spain)
Slovenija (Slovenia)
United Kingdom
United States

Link

  • riello spare parts
  • plc control cabinets
  • 空压机配件
  • 电气控制柜
  • 利雅路燃烧器